Moranbah North Mine

Back to All ProjectsMastermyne miningMastertec

Background

Moranbah North coal is mined from the Goonyella Middle Seam, approximately 200 metres below the surface. The mine currently produces 4.5 Mt annually of high fluidity premium hard coking coal mainly for export to iron and steel manufacturers in Japan, Korea and Taiwan.

Moranbah North Mine is our longest running contract site, taking in to account the consecutive contracts performed on site we have been working there for over 14 years. The current contract commenced in April 2014 and has a current end date of April 2018, with an option to extend for another 12 months.

Contract Work Scope Includes

 

Under the current structure our project team performs the following activities for the mine:

  • Secondary support activities
  • Design and installation of ventilation devices
  • Conveyor installations
  • Supply and maintain equipment
  • Supply trades to development panel
  • Supply of ancillary labour
  • Site preparation, Pre Installation and Recovery of Longwall equipment
  • Conveyor maintenance (Record breaking statistic – MG602 and MG111 Conveyor reliability over 96%)

On average we have around 130 personnel on site, plus 9 staff. Crew numbers peaking at 230 during high workloads and numerous projects operating at the same time.

In addition to these works Mastermyne have been engaged to undertake standalone development portions of work when additional drivage is required during the mine planning process.

Starting in April 2017 Mastermyne will recommence operation of a standalone development panel with an additional workforce of over 50 personnel including operators, trades, supervision and coordinators.

Chemical Injection Works

We have specialised skilled labour working within our crews at Moranbah North Mine who have undertaken the following works;

  • Drilled injection holes, packed and pumped mineral bond – LW110 chute roads
  • Drilled injection holes, packed and pumped mineral bond – LW602 chute roads
  • Drilled injection holes, packed and pumped mineral bond – LW602 seal sites due to strata failure
  • Assisted contractor pumping rocil and fennor flex on longwall face

Key Statistics

Division: Underground Mining
Client: Anglo American Australia
Location: Moranbah, QLD
Value: Umbrella works: $320M+, Drivage: $75M
Start date: 2002 (Currrent contract 2014)
Finish date: ONGOING
Key outcomes:

Development:

  • Roadway development 236m average rate, 285 best weekly metres
  • Mains and gate road drivage
  • Equipment Joy12CM12

Secondary Support:

  • megabolt installs
  • 8m mega bolts
  • 13m truss mega bolts
  • 15m truss bolts
  • 6m tendons
  • 8m bolts

Ventilation Control Devices:

  • 20psi
  • 20psi c/w hatches (Final seals)
  • Overcast
  • Machine Doors
  • Automation on machine doors
  • Regulators
  • Stoppings
  • Coffin Seals

Safety:

  • TRIFR (FY2016) – 6.88 (over 1,000,000 manhours)
  • Manhours worked (FY2016) – 290,564
  • Hazards reported:Hours worked ratio – 1:88
What we do

  In April 2015,  Mastermyne families and friends came together for a night of celebration to acknowledge the company’s loyal and long serving employees. The black tie event held at The Ocean International in Mackay recognised over 50 employees who have been with Mastermyne for more than 5 years. The 10 year service milestone was […]